IREN Q1 Results: AI Cloud Revenue Nearly Triples, ARR Target Slips to January
AI Cloud revenue rose 182% from the prior quarter to $200 million and backlog reached $20.3 billion, but the $4 billion ARR target moved to January. Shares closed Friday 20.02% above Thursday's close.

IREN Limited (NASDAQ: IREN) reported fiscal first-quarter results in an 8-K filed at 4:03 p.m. ET on Thursday, Nov. 5, in after-hours trading. Revenue was $228 million, up 66% from the prior quarter, and the net loss was $263 million. The company pushed its target of more than $4 billion in annualized run-rate revenue (ARR) to January 2027 from year-end 2026.
AI Cloud growth is real, but the ARR date moved
AI Cloud revenue of $200 million now dwarfs bitcoin mining at $28 million, so the business is clearly shifting toward AI computing. The company blamed the later ARR date on a customer-requested design change and supplier timing, and said it may extend to the end of February. The net loss narrowed from the prior quarter, but it is still large, and $6 billion of planned spending has no committed funding yet.
Shares jumped after hours and kept climbing Friday
IREN had already fallen before the report. It closed Thursday at $18.03, down 16.95%, its biggest one-day drop since Oct. 8. In after-hours trading (the session after the 4 p.m. close) on Nov. 5, shares rose 10.54% to $19.93.
On Friday, Nov. 6, the stock traded at $21.15 in pre-market, 17.3% above Thursday's close, on 10.94 million shares. The regular session closed at $21.64, up 20.02% from Thursday's close, after a range of $20.18 to $22.46. Volume was 93.80 million shares, 1.84 times the 10-day average pace. After-hours Friday, shares were at $21.81 on 2.45 million shares.
The path into the report was rough. IREN fell 8.76% on Oct. 30 and 8.06% on Nov. 2, gained 11.08% on Nov. 3, then lost 11.24% and 16.95% in the next two sessions. From Oct. 8 to Nov. 5 the stock fell 49.51%, from a high of $38.06 to a low of $17.16.
Revenue beat, earnings missed
Analysts had expected sales of $221.28 million, so $228 million was a beat. The loss of $0.66 per share was wider than the $0.48 loss analysts had expected. Revenue was below the $240 million of a year earlier.
The backlog, the revenue the company expects from signed contracts, reached $20.3 billion, up 22% from the prior quarter, with about two-thirds from investment-grade counterparties. IREN's market capitalization was about $8.76 billion. After the quarter ended, it signed a five-year contract at about $22 million per megawatt, with the customer prepaying 90% of the GPU capital spending, and a short-term contract at $40 million per megawatt.
What changed in the quarter
- AI Cloud revenue: $200 million, up from $71 million. It included $135 million of services and $65 million of lease revenue, which was zero a quarter earlier.
- Bitcoin mining revenue: $28 million, down from $67 million.
- AI Cloud gross margin: 86%, in line with the prior quarter.
- Adjusted EBITDA: $66 million, up from $19 million. Net loss was $263 million, against $684 million a quarter earlier.
- Pricing: contracted prices rose 11% on three-year deals and 12% on five-year deals.
- Balance sheet: data center assets of $6 billion make up part of total assets of $20.6 billion.
- Funding: $15 billion of remaining planned fiscal 2027 capital spending. The company said $9 billion is covered by cash, committed GPU financing and customer prepayments. The other $6 billion depends on financing subject to market conditions.
IREN also said it is making a network design change across its Horizon sites at Microsoft's request. Under the Microsoft agreement, delivery dates are extended, without delay credits, for delays that change causes. The company said it expects to keep making large investments, including GPU purchases and new data center capacity.
The company describes ARR as an operating measure, not GAAP revenue, and said recognized revenue could be materially lower.
What to watch next
- Jan. 31, 2027: the company's target date for more than $4 billion of ARR, which it said may extend to the end of February.
- Horizon 2-4: the company said these sites are in late-stage construction after Horizon 1 went into service for Microsoft.
- The remaining $6 billion of financing, which depends on market conditions.
- Commissioning, testing and customer acceptance, which the company said set when revenue ramps after each data center is delivered.
Bottom line
IREN reported faster AI Cloud growth, a steady 86% segment margin and a larger backlog, and the stock closed Friday 20.02% above Thursday's close. The later ARR date, the $263 million net loss and the unfunded $6 billion of spending are the open items.